West Ealing Area Crossrail Works - Saturday 31 October - Friday 27 November 2015


West Ealing Area Crossrail Works: Information Bulletin Saturday 31 October - Friday 27 November 2015

This bulletin provides local residents with an outline of the work Network Rail and our contractors are undertaking in the coming weeks in your area. All works highlighted in bold may generate some noise or disturbance which residents may notice.

Crossrail works here will change and improve the station, create a new bay platform and enlarge platform 4 on the north side of the station. For more information on this work please visit: http://www.crossrail.co.uk/route/western-section/west-ealing-station

Please note that current works during the day are at a higher noise level than normal and residents may notice them over general background noise.

Saturday 31 October to Friday 6 November

page1image7336 page1image7496

Monday to Sunday daytime 08:00 18:00

page1image10712

Works in the rail compound at the far west end of Manor Road and the site compound at the east end of Manor Road.

page1image12928

Sunday morning 05:30 07:00

Team of workers and more road rail vehicles will arrive and make their way to the west end of Waitrose Car Park where groups of rail vehicles with supporting foot workers will make their way to different points between West Ealing and Hanwell Stations and set up work sites.

Sunday 07:00 08:00

A pile, previously half driven into the railway lineside beside West Ealing Station (north of the Waitrose delivery yard) will be hammered to full depth. This will take about 20 mins, only taking longer if there are unexpected ground issues.

Sunday 08:00 09:00

The piling rigs will dismount from the track and be reloaded onto lorries to leave the area by 09:30.
Rail cranes/elevated working platforms will move to the station area to secure a mast and boom in the location piled earlier.

Sunday 09:00 22:00

Mobile elevated platforms and cranes will continue to work all day so the new overhead line equipment is complete with overhead wires moved to the new supports.

Weekend nights 21:00 22:00 Weekend mornings 09:00 10:00

Preparation/finishing works for the night shift including starting up plant, moving materials and fences

Monday to Thursday 22:00 05:00

Replacement of electrical systems on the track, working east and west from West Ealing.

Every night of the week

A low loader (or two) may drop off road rail vehicles at the west end of Manor Road or the Waitrose car park off Alexandria Road in the evening and pick them up the following morning.

Saturday 7 to Friday 13 November

page1image42936

Monday to Sunday daytime 08:00 18:00

Works in the rail compound at the far west end of Manor Road and the site compound at the east end of Manor Road.

Weekend nights 21:00 22:00 Weekend mornings 09:00 10:00

Preparation/finishing works for the night shift including starting up plant and moving materials and fences

Saturday 22:00 to Monday 04:00

Breaking out of concrete and installation of duct routes on platform 4. Excavation works and installation of trench sheets on platform 2/3.

Saturday 22:00 to Sunday 22:00

Use of elevated work platforms and a cable drum carrying machine to alter overhead power lines between Argyle Road and the west end of Felix Road

Saturday 23:00 to Sunday 06:00

Use of 2 rail mounted piling machines (1 vibrating and 1 hammer) to pile foundations for new overhead line system posts on the north side of the railway lines between St Leonards Road bridge and Jacobs Ladder footbridge. This work should take around 3-4 hours.

Weekdays 21:00 06:00

Use of elevated work platforms to adjust the overhead power supplies between

Network Rail Infrastructure Limited Registered Office: Network Rail, 2nd Floor, One Eversholt Street, London, NW1 2DN Registered in England and Wales No. 2904587 www.networkrail.co.uk

page2image440

Ealing Broadway and Hanwell. May also require 2 or 3 machines to install new under-track cable crossings.

Every night of the week

Installation of ducts on platform 4.
A low loader (or two) may drop off road rail vehicles at the west end of Manor Road or the Waitrose car park off Alexandria Road in the evening and pick them up the following morning.

Saturday 14 to Friday 20 November

Saturday 21 to Friday 27 November

page2image11072

Monday to Sunday daytime 08:00 18:00

Works in the rail compound at the far west end of Manor Road and the site compound at the east end of Manor Road.

Saturday 22:00 to Sunday 09:00

Breaking out of concrete and installation of duct routes on the platform 4. Excavation works and installation of trench sheets on platform 2/3. A piling machine on platform 2/3 installing bored piles.

Every night of the week

page2image22648

Installation of ducts on platform 4.
A piling machine on platform 2/3 installing bored piles.

page2image24672

Monday to Sunday daytime 08:00 18:00

page2image28032

Works in the rail compound at the far west end of Manor Road and the site compound at the east end of Manor Road.

Saturday 22:00 to Monday 04:00

Excavation works and installation of trench sheets on platform 2/3. A piling machine on platform 2/3 installing bored piles.

Saturday 22:00 to Sunday 20:00

Delivery of track sections to the west end of Manor Road by lorry and lifting off by large crane (delivered Saturday daytime). This work requires shutting the rail lines on north side of West Ealing and the Greenford Line to be carried out safely. Delivery of cable ducting to the west end of Manor Road.

Weekdays 21:00 to 06:00

Installation of cable ducting on the main lines (south side) of West Ealing using track trollies and possibly a road rail machine.

Every night of the week

A piling machine on platform 2/3 installing bored piles.
A low loader (or two) may drop off road rail vehicles at the west end of Manor Road or the Waitrose car park off Alexandria Road in the evening and pick them up the following morning.

West Ealing also contains railway depots and places where railway maintenance rail machines can gain access to the track during night shifts. Please note works by these companies and rail bodies are not covered in this Crossrail works bulletin.

Our contractors undertaking the above work are part of the Considerate Constructors Scheme, which includes minimising any environmental impacts and working to reduce the impact on neighbours and the public. Although we aim to undertake works at the above times and dates, at times last minute changes to track closures may result in variations.

If you have any additional questions relating to the content of this bulletin please contact us on CRCrossrail@networkrail.co.uk or through our 24-Hour National Helpline on 03457 11 41 41.

page2image54640

Network Rail Infrastructure Limited Registered Office: Network Rail, 2nd Floor, One Eversholt Street, London, NW1 2DN Registered in England and Wales No. 2904587 www.networkrail.co.uk ;

Views: 24

Add a Comment

You need to be a member of Draytons Community Association to add comments!

Join Draytons Community Association

© 2019   Created by Gerald Power.   Powered by

Badges  |  Report an Issue  |  Terms of Service